THREE control kiosks are due to be built at the wastewater treatment works at Carlisle Close, Mobberley.
Planning permission for the scheme is being sought from Cheshire East Council.
The proposed scheme involves the installation of new wastewater treatment infrastructure to accommodate population growth and improvements to the receiving watercourse.
Site activities were due to start this month with site clearance, compound set-up and the installation of a temporary haul road.
The construction programme is due to last for 74 weeks, and the installation of the kiosks is due to start in January 2021.